Application
Cooler ESP of a cement plant located in Cambodia.
Problem
- Unstable operation of controller
- Worn out mechanical parts & misalignment problem
- Worn out original top rapping system, including loose connection, and broken shaft
Solution
The overhaul maintenance & modification works were carried out within 12 days working 2 shifts / 24 hours:
- Design & modification of DE rapping system from top rapping to side rapping
- Supply of new DE frame & installation supervision
- GVC controller installation
- Supply of minor parts such as CP hammer, insulator, etc.
- Installation of walkway
Limitations & difficulties encountered during maintenance:
- Modification work: Due to the alignment of H beam and rapping shaft, the rapping insulator box with dust removal screw could not be installed directly.
Solution: Minor modification of H beams and DE rapping shaft location was carried out.
- Electrical: 1 keypad to control 3 mainboards.
Solution: Use networking connection and apply on/off push button to control the ESP in case the keypad faces malfunctioning problem.






Benefits
No load test was carried out after installation. ESP was operating efficiently with stable performance.
Field Number | Before (Load Test) | After (No-Load Test) |
Field 1 | 0kV/146mA (swing kV) | 42kV/678mA |
Field 2 | 36kV/541mA | 38kV/729mA |
Field 3 | 55kV/467mA | 42kV/727mA |





